Greater Plutonio Project delivering world-class wells in deepwater Angola

Posted on 13 October 2008

The Sedco Express is one of only three enhanced-activity drilling rigs in its class. Prior to commencing work on the Plutonio Project, it underwent four major upgrades: thrusters were replaced, blisters were installed for extra deck loading and stability, an additional drilling station was installed and an additional ROV was stationed aboard.

A multidisciplinary planning team was formed in Sunbury, United Kingdom that embarked on a three-year pre-planning process, eventually defining a 43-well development program offshore Angola.  The team also identified necessary rig specifications and upgrades.  Standardized well plans included casing designs for shallow gas and no shallow gas, and standardized hole sizes for producing wells and injection wells.

The start-up team included employees of eight nationalities. Once the project got under way, this quickly expanded to 43 nationalities operating offshore.  “Even though English was the common language, communications problems resulted from this diversity,” Mr Gilbertson said. “However, this diversity also provided us with wide-ranging and highly skilled technical experience from different parts of the globe, which eventually worked to our benefit.”

Safety leadership training was conducted in both Brazil and Luanda, with major emphasis placed on mid-level leaders such as drillers and assistant drillers.  
Continuous improvement was an essential part of the project that was ingrained in the process at an early stage.

“Our first top hole took six days,” Mr Gilbertson said. “We took photos, recorded data, and used this to hone procedures that were implemented for the remaining top hole sections. We were later doing top holes in less than two days.”

Continuous improvement coaches were stationed offshore to expedite the transfer of lessons within the team.  These were supplemented by ongoing DWOP and CWOP, post-section and post-well reviews, weekly continuous improvement process (CIP) meetings, quarterly contractor reviews, and ongoing CIP implementation tracking.

In closing his presentation, Mr Gilbertson gave credit for the success of the Plutonio Project to the Sedco Express and the Block 18 team. “This is the most high tech we have in Angola — rig and its personnel. That’s the secret to our success – Sedco Express and the people who work it.”

Leave a Reply

*

FEATURED MICROSITES


Recent Drilling News

  • 31 October 2014

    Japan Drilling to operate new jackup under construction at Keppel

    The KFELS Super B Class design has a drilling depth of 35,000 ft. The rig's leg structure is designed to provide enhanced robustness for operations at 400 ft water depth...

  • 29 October 2014

    New intelligent water management solution based on oxidizer technology

    Nalco Champion has launched the RenewIQ line of oilfield water reuse solutions to help operators reduce freshwater consumption and associated handling costs...

  • 29 October 2014

    Baker Hughes launches all-electric intelligent well system

    Baker Hughes has commercially released its MultiNode all-electric intelligent well system. It allows operators to remotely monitor and control a greater number of production zones...

  • 29 October 2014

    Tercel collaborates with TOTAL to design MicroCORE PDC drill bit

    Tercel Oilfield Products has launched the MicroCORE cutting system at the 2014 SPE Annual Technical Conference and Exhibition in Amsterdam. The MicroCORE cutting...

  • 28 October 2014

    First extension well in pre-salt Libra leads to oil discovery

    The Libra consortium announced that the drilling of the first extension well in the Libra area, known as 3-BRSA-1255-RJS (3-RJS-731), has proven the discovery of high-quality oil...

  • Read more news