Greater Plutonio Project delivering world-class wells in deepwater Angola

Posted on 13 October 2008

The Sedco Express is one of only three enhanced-activity drilling rigs in its class. Prior to commencing work on the Plutonio Project, it underwent four major upgrades: thrusters were replaced, blisters were installed for extra deck loading and stability, an additional drilling station was installed and an additional ROV was stationed aboard.

A multidisciplinary planning team was formed in Sunbury, United Kingdom that embarked on a three-year pre-planning process, eventually defining a 43-well development program offshore Angola.  The team also identified necessary rig specifications and upgrades.  Standardized well plans included casing designs for shallow gas and no shallow gas, and standardized hole sizes for producing wells and injection wells.

The start-up team included employees of eight nationalities. Once the project got under way, this quickly expanded to 43 nationalities operating offshore.  “Even though English was the common language, communications problems resulted from this diversity,” Mr Gilbertson said. “However, this diversity also provided us with wide-ranging and highly skilled technical experience from different parts of the globe, which eventually worked to our benefit.”

Safety leadership training was conducted in both Brazil and Luanda, with major emphasis placed on mid-level leaders such as drillers and assistant drillers.  
Continuous improvement was an essential part of the project that was ingrained in the process at an early stage.

“Our first top hole took six days,” Mr Gilbertson said. “We took photos, recorded data, and used this to hone procedures that were implemented for the remaining top hole sections. We were later doing top holes in less than two days.”

Continuous improvement coaches were stationed offshore to expedite the transfer of lessons within the team.  These were supplemented by ongoing DWOP and CWOP, post-section and post-well reviews, weekly continuous improvement process (CIP) meetings, quarterly contractor reviews, and ongoing CIP implementation tracking.

In closing his presentation, Mr Gilbertson gave credit for the success of the Plutonio Project to the Sedco Express and the Block 18 team. “This is the most high tech we have in Angola — rig and its personnel. That’s the secret to our success – Sedco Express and the people who work it.”

Leave a Reply

*

Recent Drilling News

  • 14 June 2013

    UK HSE report: Reportable hydrocarbon releases nearly halved over three years

    The UK oil and gas industry has achieved a 48% reduction in the number of reportable hydrocarbon releases over three years, the...

  • 12 June 2013

    Atwood Oceanics secures contract for Atwood Achiever ultra-deepwater drillship

    Atwood Oceanics has been awarded a drilling services contract for the ultra-deepwater drillship Atwood Achiever by a subsidiary...

  • 10 June 2013

    Ensco orders its eighth Samsung DP3 ultra-deepwater drillship

    Ensco has ordered an additional advanced-capability DP3 ultra-deepwater drillship based on the Samsung GF12000 hull design. The vessel, ENSCO DS-10, will be the eighth...

  • 07 June 2013

    Unconventionals lead the way for drilling automation, but business model defines uptake

    Industry’s ongoing efforts to bring automation to the drilling sector will progress over time as a “natural alignment”...

  • 05 June 2013

    Exclusive video: Compact top drive, casing drive system built for mobility

    Julio Quintana, president and CEO for Tesco, speaks with Drilling Contractor associate editor Katherine Scott...

  • Read more news