Greater Plutonio Project delivering world-class wells in deepwater Angola

Posted on 13 October 2008

The Sedco Express is one of only three enhanced-activity drilling rigs in its class. Prior to commencing work on the Plutonio Project, it underwent four major upgrades: thrusters were replaced, blisters were installed for extra deck loading and stability, an additional drilling station was installed and an additional ROV was stationed aboard.

A multidisciplinary planning team was formed in Sunbury, United Kingdom that embarked on a three-year pre-planning process, eventually defining a 43-well development program offshore Angola.  The team also identified necessary rig specifications and upgrades.  Standardized well plans included casing designs for shallow gas and no shallow gas, and standardized hole sizes for producing wells and injection wells.

The start-up team included employees of eight nationalities. Once the project got under way, this quickly expanded to 43 nationalities operating offshore.  “Even though English was the common language, communications problems resulted from this diversity,” Mr Gilbertson said. “However, this diversity also provided us with wide-ranging and highly skilled technical experience from different parts of the globe, which eventually worked to our benefit.”

Safety leadership training was conducted in both Brazil and Luanda, with major emphasis placed on mid-level leaders such as drillers and assistant drillers.  
Continuous improvement was an essential part of the project that was ingrained in the process at an early stage.

“Our first top hole took six days,” Mr Gilbertson said. “We took photos, recorded data, and used this to hone procedures that were implemented for the remaining top hole sections. We were later doing top holes in less than two days.”

Continuous improvement coaches were stationed offshore to expedite the transfer of lessons within the team.  These were supplemented by ongoing DWOP and CWOP, post-section and post-well reviews, weekly continuous improvement process (CIP) meetings, quarterly contractor reviews, and ongoing CIP implementation tracking.

In closing his presentation, Mr Gilbertson gave credit for the success of the Plutonio Project to the Sedco Express and the Block 18 team. “This is the most high tech we have in Angola — rig and its personnel. That’s the secret to our success – Sedco Express and the people who work it.”

Leave a Reply

*

FEATURED MICROSITES


Recent Drilling News

  • 22 August 2014

    Ryan Directional Services inks deal to deploy Alcoa pipe in North American shales

    Ryan Directional Services, a division of Nabors, has selected Alcoa’s FarReach alloy drill pipe for its onshore horizontal-drilling applications…

  • 18 August 2014

    Repsol runs BlueDock connectors in Trinidad and Tobago

    Repsol has recently run BlueDock connectors with elastomeric seals in Trinidad and Tobago. The operation took place in the Arima 2 well on a jackup platform...

  • 15 August 2014

    Joe Hurt to retire from IADC

    After more than 14 years with IADC and a career spanning 42 years, Joe Hurt, Vice President of IADC’s Onshore Division, will retire at the end of August. Mr Hurt began his career in 1974 with Noble Corp, working on land drilling rigs...

  • 13 August 2014

    OneSubsea, Helix and Schlumberger to form subsea well intervention alliance

    OneSubsea, Helix Energy Solutions Group and Schlumberger have entered into a letter of intent to form an alliance to develop technologies and deliver...

  • 12 August 2014

    Noble Energy, Woodside Petroleum sign PSC for exploration offshore Gabon

    Noble Energy has signed a production-sharing contract (PSC) with Gabon government, covering Block F15 in the Gabon Coastal Basin. Under the terms...

  • Read more news