CATEGORIZED | News

MPD campaign in Gulf of Thailand slashes NPT

Posted on 26 February 2010

By using MPD, ECD can be managed more closely. Other advantages include maintaining wellbore stability, avoiding losses, improving drilling efficiency and reducing cost.

By using MPD, ECD can be managed more closely. Other advantages include maintaining wellbore stability, avoiding losses, improving drilling efficiency and reducing cost.

A two-year, nine-well MPD campaign in the Gulf of Thailand resulted in dramatic improvements in nonproductive time and overall drilling performance, reports a paper presented at the 2010 SPE/IADC Managed Pressure Drilling & Underbalanced Operations Conference, 24-25 February in Kuala Lumpur.

The paper was presented by Paul Fredericks, At Balance with Smith, who stressed that this was not a case of MPD drilling “undrillable” wells. “The operator had good drilling practices and kept the hole clean,” Mr Fredericks said. “It was the time that it was taking to keep the well clean with good equivalent circulating density (ECD) that was the issue.”

MPD was used to drill through a depleted zone and to reduce NPT, and therefore cost, compared with previous operations drilled conventionally.

“In the conventional scenario,” Mr Fredericks said, “the mud weight was 10.5 ppg.” MPD allowed the operator to decrease the mud weight to 9.0, a 1.5-ppg savings.

“Herein lies an important point for managed pressure drilling – that MPD is a true enabling technology,” he added.

As a consequence of the reduced mud weight, the ECD fell from 12.5 ppg to 10.59 ppg. The 2.0-ppg difference was critical. Any higher than 11.9 and the ECD would’ve exceeded the fracture gradient. Mr Fredericks said that drilling was possible without losses because ECDs were below 11.3 ppg. However, this choked performance, requiring cutbacks on ROP and flow rate, restrictions on string rotation speed, and use of high pV and solids concentrations.

And, importantly, each connection required two to three back-reaming operations.

Still, on the first MPD well, back-reaming was required. “In any long-term MPD project, there is a learning curve,” Mr Fredericks said.

By the fifth well, the operator decided to drill out of the 9 5/8-in. shoe with MPD rather than the conventional approach. This resulted in 800 m drilled in two days, or 400 m/day, compared with less than 300 m/day on a conventional offset.

Mr Fredericks noted that back-reaming was still required; however, this fell to twice per connection, rather than three times.

Due to a problem with a seal, the operator chose to switch to conventional operations in the 8-in. section. Resulting ROP fell dramatically to 87 m/day.

ECD profiles also changed for the better with the use of MPD. The ECD spiked significantly (approximately 1 ppg peak to peak) in conventional drilling, due to swab and surge caused by back-reaming. In the first MPD well, using 9-ppg mud and a higher flow rate, ECD was flat at 11 ppg. In the seventh well, ECD ranged between 10.5-11 ppg. Surge and swab was experienced, but less back-reaming was required.

A two-year, nine-well MPD campaign in the Gulf of Thailand resulted in dramatic improvements in nonproductive time and overall drilling performance, reports a paper presented at the 2010 SPE/IADC Managed Pressure Drilling & Underbalanced Operations Conference, 24-25 February in Kuala Lumpur.
The paper was presented by Paul Fredericks, At Balance with Smith, who stressed that this was not a case of MPD drilling “undrillable” wells. “The operator had good drilling practices and kept the hole clean,” Mr Fredericks said. “It was the time that it was taking to keep the well clean with good equivalent circulating density (ECD) that was the issue.”
MPD was used to drill though a depleted zone and to reduce NPT, and therefore cost, compared with previous operations drilled conventionally.
“In the conventional scenario,” Mr Fredericks said, “the mud weight was 10.5 ppg. MPD allowed the operator to decrease the mud weight to 9.0, a 1.5 ppg savings.
“Herein lies an important point for managed pressure drilling – that MPD is a true enabling technology,” he added.
As a consequence of the reduced mud weight, the ECD fell from 12.5 ppg to 10.59 ppg. The 2.0-ppg difference was critical. Any higher than 11.9 and the ECD would’ve exceeded the fracture gradient. Mr Fredericks said that drilling was possible without losses because ECDs were below 11.3 ppg. However, this choked performance, requiring cutbacks on ROP and flow rate, restrictions on string rotation speed, and use of high pV and solids concentrations. And, importantly, each connection required two to three back-reaming operations.
Still, on the first MPD well, back-reaming was required. “In any long-term MPD project, there is a learning curve,” Mr Fredericks said.
By the fifth well, the operator decided to drill out of the 9 5/8-in. shoe with MPD rather than the conventional approach. This resulted in 800 m drilled in two days, or 400 m/day, compared with less than 300 m/day on a conventional offset.
,Mr Fredericks noted that back-reaming was still required; however, this fell to twice per connection, rather than three times.
Due to a problem with a seal, the operator chose to switch to conventional operations in the 8-in. section. Resulting ROP fell dramatically to 87 m/day.
ECD profiles also changed for the better with the use of MPD. The ECD spiked significantly (approximately 1 ppg peak to peak) in conventional drilling, due to swab and surge caused by back-reaming. In the first MPD well, using 9-ppg mud and a higher flow rate, ECD was flat at 11 ppg. In the seventh well, ECD ranged between 10.5-11 ppg. Surge and swab was experienced, but less back-reaming was required.

Leave a Reply

*

FEATURED MICROSITES


Recent Drilling News

  • 22 August 2014

    Ryan Directional Services inks deal to deploy Alcoa pipe in North American shales

    Ryan Directional Services, a division of Nabors, has selected Alcoa’s FarReach alloy drill pipe for its onshore horizontal-drilling applications…

  • 18 August 2014

    Repsol runs BlueDock connectors in Trinidad and Tobago

    Repsol has recently run BlueDock connectors with elastomeric seals in Trinidad and Tobago. The operation took place in the Arima 2 well on a jackup platform...

  • 15 August 2014

    Joe Hurt to retire from IADC

    After more than 14 years with IADC and a career spanning 42 years, Joe Hurt, Vice President of IADC’s Onshore Division, will retire at the end of August. Mr Hurt began his career in 1974 with Noble Corp, working on land drilling rigs...

  • 13 August 2014

    OneSubsea, Helix and Schlumberger to form subsea well intervention alliance

    OneSubsea, Helix Energy Solutions Group and Schlumberger have entered into a letter of intent to form an alliance to develop technologies and deliver...

  • 12 August 2014

    Noble Energy, Woodside Petroleum sign PSC for exploration offshore Gabon

    Noble Energy has signed a production-sharing contract (PSC) with Gabon government, covering Block F15 in the Gabon Coastal Basin. Under the terms...

  • Read more news