CATEGORIZED | News

MPD campaign in Gulf of Thailand slashes NPT

Posted on 26 February 2010

By using MPD, ECD can be managed more closely. Other advantages include maintaining wellbore stability, avoiding losses, improving drilling efficiency and reducing cost.

By using MPD, ECD can be managed more closely. Other advantages include maintaining wellbore stability, avoiding losses, improving drilling efficiency and reducing cost.

A two-year, nine-well MPD campaign in the Gulf of Thailand resulted in dramatic improvements in nonproductive time and overall drilling performance, reports a paper presented at the 2010 SPE/IADC Managed Pressure Drilling & Underbalanced Operations Conference, 24-25 February in Kuala Lumpur.

The paper was presented by Paul Fredericks, At Balance with Smith, who stressed that this was not a case of MPD drilling “undrillable” wells. “The operator had good drilling practices and kept the hole clean,” Mr Fredericks said. “It was the time that it was taking to keep the well clean with good equivalent circulating density (ECD) that was the issue.”

MPD was used to drill through a depleted zone and to reduce NPT, and therefore cost, compared with previous operations drilled conventionally.

“In the conventional scenario,” Mr Fredericks said, “the mud weight was 10.5 ppg.” MPD allowed the operator to decrease the mud weight to 9.0, a 1.5-ppg savings.

“Herein lies an important point for managed pressure drilling – that MPD is a true enabling technology,” he added.

As a consequence of the reduced mud weight, the ECD fell from 12.5 ppg to 10.59 ppg. The 2.0-ppg difference was critical. Any higher than 11.9 and the ECD would’ve exceeded the fracture gradient. Mr Fredericks said that drilling was possible without losses because ECDs were below 11.3 ppg. However, this choked performance, requiring cutbacks on ROP and flow rate, restrictions on string rotation speed, and use of high pV and solids concentrations.

And, importantly, each connection required two to three back-reaming operations.

Still, on the first MPD well, back-reaming was required. “In any long-term MPD project, there is a learning curve,” Mr Fredericks said.

By the fifth well, the operator decided to drill out of the 9 5/8-in. shoe with MPD rather than the conventional approach. This resulted in 800 m drilled in two days, or 400 m/day, compared with less than 300 m/day on a conventional offset.

Mr Fredericks noted that back-reaming was still required; however, this fell to twice per connection, rather than three times.

Due to a problem with a seal, the operator chose to switch to conventional operations in the 8-in. section. Resulting ROP fell dramatically to 87 m/day.

ECD profiles also changed for the better with the use of MPD. The ECD spiked significantly (approximately 1 ppg peak to peak) in conventional drilling, due to swab and surge caused by back-reaming. In the first MPD well, using 9-ppg mud and a higher flow rate, ECD was flat at 11 ppg. In the seventh well, ECD ranged between 10.5-11 ppg. Surge and swab was experienced, but less back-reaming was required.

A two-year, nine-well MPD campaign in the Gulf of Thailand resulted in dramatic improvements in nonproductive time and overall drilling performance, reports a paper presented at the 2010 SPE/IADC Managed Pressure Drilling & Underbalanced Operations Conference, 24-25 February in Kuala Lumpur.
The paper was presented by Paul Fredericks, At Balance with Smith, who stressed that this was not a case of MPD drilling “undrillable” wells. “The operator had good drilling practices and kept the hole clean,” Mr Fredericks said. “It was the time that it was taking to keep the well clean with good equivalent circulating density (ECD) that was the issue.”
MPD was used to drill though a depleted zone and to reduce NPT, and therefore cost, compared with previous operations drilled conventionally.
“In the conventional scenario,” Mr Fredericks said, “the mud weight was 10.5 ppg. MPD allowed the operator to decrease the mud weight to 9.0, a 1.5 ppg savings.
“Herein lies an important point for managed pressure drilling – that MPD is a true enabling technology,” he added.
As a consequence of the reduced mud weight, the ECD fell from 12.5 ppg to 10.59 ppg. The 2.0-ppg difference was critical. Any higher than 11.9 and the ECD would’ve exceeded the fracture gradient. Mr Fredericks said that drilling was possible without losses because ECDs were below 11.3 ppg. However, this choked performance, requiring cutbacks on ROP and flow rate, restrictions on string rotation speed, and use of high pV and solids concentrations. And, importantly, each connection required two to three back-reaming operations.
Still, on the first MPD well, back-reaming was required. “In any long-term MPD project, there is a learning curve,” Mr Fredericks said.
By the fifth well, the operator decided to drill out of the 9 5/8-in. shoe with MPD rather than the conventional approach. This resulted in 800 m drilled in two days, or 400 m/day, compared with less than 300 m/day on a conventional offset.
,Mr Fredericks noted that back-reaming was still required; however, this fell to twice per connection, rather than three times.
Due to a problem with a seal, the operator chose to switch to conventional operations in the 8-in. section. Resulting ROP fell dramatically to 87 m/day.
ECD profiles also changed for the better with the use of MPD. The ECD spiked significantly (approximately 1 ppg peak to peak) in conventional drilling, due to swab and surge caused by back-reaming. In the first MPD well, using 9-ppg mud and a higher flow rate, ECD was flat at 11 ppg. In the seventh well, ECD ranged between 10.5-11 ppg. Surge and swab was experienced, but less back-reaming was required.

Leave a Reply

*

FEATURED MICROSITES


Recent Drilling News

  • 15 September 2014

    US Treasury announces expanded sanctions with Russian companies

    US Treasury Secretary Jacob J. Lew has announced that persons operating within Russia’s defense and related materiel sector may now be subject to targeted sanctions…

  • 11 September 2014

    Cameron elects Scott Rowe as President and COO

    Scott Rowe will assume the newly created position of President and COO of Cameron, effective 1 October 2014. In his new role, he will report directly to Jack Moore, Chairman and CEO of the company...

  • 11 September 2014

    Statoil, GE and Ferus Natural Gas Fuels expand flare gas solution in Bakken

    A joint venture of GE and Ferus Natural Gas Fuels (Ferus NGF), along with Statoil plan to expand a pilot project to capture flare gas and use it to power up to six...

  • 10 September 2014

    6 elements of successful collaboration among NOCs, IOCs, service companies

    The oil and gas landscape is shifting, with the continuing growth of NOCs and the industry going toward unconventional resources and new frontiers…

  • 09 September 2014

    PTTEP: NOCs, IOCs and service companies must combine strengths to overcome challenges

    As assets become more mature and operations become more complex, industry is challenged with finding economical and environmentally friendly operating strategies...

  • Read more news