Operational experience, contingency planning fill gaps in deepwater cementing

Posted on 08 May 2012

By Joanne Liou, editorial coordinator

Ragheb Dajani of Hess Corp provided an operational perspective on using cement as a primary barrier in deepwater wells at the 2012 OTC on 30 April in Houston.

Two questions need to be asked when considering cement as a primary barrier in a deepwater well: 1) Will the job be successful? 2) What if it isn’t? The two considerations beg to question and validate the prospect of a successful cementing operation. Ragheb Dajani of Hess Corp shared an operational perspective on cementing during a keynote speech at the 2012 OTC on 30 April in Houston. “There is a definite increase in recognition and scrutiny on the profound effects cementing can have on operations – on safety, environment and public opinion,” he said, “but the gap is in installing the cement as the barrier downhole.”

On paper, a lot has been done to support cement designs; however, there is uncertainty in effectively executing the operation.

It is important to understand the risks of a cementing operation and to approach it from a perspective that realizes the consequences of failure, Mr Dajani explained. A key challenge is in the cementing design, and the first step is to determine whether cement can realistically provide a barrier. “We can’t always rely on cementing unless we have a high degree of confidence to execute it and to provide a barrier downhole,” he said. “As we go deeper and deeper into the reservoirs, we’re asking for a small volume of cement to travel four or five miles. Yes, we can do that, but there is a lot of work that needs to be done ahead of time in order to protect that cement slurry to reach 20,000 ft.”

A strong understanding of the wellbore environment and the effects of contaminants on the cement slurry are among considerations that need to be addressed ahead of time. “Do we have adequate compressive strength development? Do we need to wait for the cement for a longer period of time until the contaminant actually sets to have an isolation barrier off the cement?”

As the cement is loaded offshore, it travels through a chain of custody that calls for quality control and brings Mr Dajani to pose more questions. “Are we using the right pressure on the lines? Is there too much moisture?” Quality control is necessary for the cement to maintain its chemical properties and a successful end result, he said.

On the training side, young engineers may have the knowledge but still lack field experience. An understanding of best practices cannot replace experience. “There’s a disconnect between designing on paper and having the experience level to have confidence in executing it in the field,” Mr Dajani stated. The challenge can be met by providing them with additional time and field training offshore.

Leave a Reply

*

FEATURED MICROSITES


Recent Drilling News

  • 01 October 2014

    Video: Schlumberger mapping-while-drilling service expands view around wellbore

    GeoSphere, Schlumberger’s new reservoir mapping-while-drilling service, optimizes well placement operations and steering capabilities with deep-directional...

  • 30 September 2014

    Statoil, Shell and Sonatrach awarded acreage onshore Algeria

    Statoil and Shell were awarded the Timissit Permit License in the Illizi-Ghadames Basin onshore Algeria. The license is in southeastern Algeria and covers an area of 2,730 sq km...

  • 29 September 2014

    Rosneft discovers oil in Kara Sea

    Rosneft successfully completed the drilling of the Universitetskaya-1 well in the Arctic – the northernmost well in the world, according to the company, and discovered oil at the East-Prinovozemelskiy-1 license area...

  • 26 September 2014

    Statoil and PL713 partners discover gas in Pingvin prospect in Barents Sea

    Statoil has together with PL713 partners made a gas discovery in the Pingvin prospect in the Barents Sea. The discovery is a play opener in an unexplored frontier…

  • 26 September 2014

    Maersk Drilling names fourth ultra-deepwater drillship, delivery expected in Q4

    Maersk Drilling’s fourth ultra-deepwater drillship was named Thursday morning in a ceremony at the Samsung Heavy Industries (SHI) shipyard in Geoje-Si...

  • Read more news