To be effective, leaders can’t just ‘wing’ offshore site visits

Posted on 13 February 2013

By Linda Hsieh, managing editor

The Center for Offshore Safety began work in 2012 on a guidance document on how office-based leadership should show up offshore and effectively lead safety. Alan Quintero, Transocean SVP Americas, provided an update on the guidelines at the 2013 IADC HSE & Training Conference on 6 February in Houston, noting that a final version is expected to be published this year.

A guidance document under development at the Center for Offshore Safety (COS) aims to help office-based leadership make the most out of their visits to the worksite and demonstrate visible commitment to safety. The guidelines, which are under final review with a COS committee made up of operators, drilling contractors and service and supply representatives, are expected to be published this year, Alan Quintero, Transocean SVP Americas and a member of the COS Governing Board, said at the 2013 IADC HSE & Training Conference last week in Houston. “To be effective offshore, you can’t just show up and wing it,” he said, adding that preparation is the first of three main sections in the COS Leadership Site Engagement guidelines. Execution and closure are the other two.

“To me, leadership site engagement is avoiding what I call ‘seagull management,’ where you fly in, you leave your droppings on everything, and then fly away. That’s not what you want to do. You want to actually make an impact and walk out of there feeling that the processes, policies and procedures that you’ve put in place as a leader of the company are being followed the way you thought they should be followed,” Mr Quintero said.

While preparing for the site visit, company leaders need to understand what are the current activities going on at the worksite and what are the hazards associated with those activities. “What do you want to evaluate when you’re onboard? Culture? Policies and procedures? Make yourself a plan,” Mr Quintero advised. A sit-down with subject matter experts on the subsea group may be beneficial if you’re going to visit with personnel on the specifics of BOP equipment, for example.

The execution phase of the leadership site engagement needs to start with a thorough site orientation, followed by the company’s safety induction process. “Don’t take shortcuts. You’re leading by example,” Mr Quintero noted. “Your at-risk behavior – like skipping through the safety orientation or not knowing where your lifeboats are – all those types of things get observed by people at the worksite.”

Leaders should also make time for meetings with the site leadership and contractor leaders, where the objectives of the visit should be clearly explained. “Only after everybody is lined up with the plan and what you’re trying to accomplish, then you go and walk around the site,” Mr Quintero said.

After the walkaround, a meeting should be held with your workforce, contractors and especially the site leadership team to share your learnings and to put together a closure plan with follow-up actions. “Show that your meeting was important and you’re following through to provide that level of accountability with the people at the worksite,” he urged.

Mr Quintero also noted that the COS document is meant to be only a guidance to help industry leadership further drive safety processes at worksites; it is not a mandate. “Depending on how mature your systems are, you can pick and choose from it the parts that will help you make your leadership site engagements better.”

The COS expects to provide another update on this guidance document at its first annual forum on 29-30 April in Houston. Click here for more information.

 

Leave a Reply

*

FEATURED MICROSITES


Recent Drilling News

  • 25 November 2014

    Prescriptive Analytics prescribes how to complete wells to maximize production

    "Big data" is taking on a new role in industry, where companies are combining the findings from geology and geophysics with new data collected from advanced technologies...

  • 25 November 2014

    Petrobras completes drilling first appraisal well in Libra Consortium

    Petrobras recently completed drilling the first appraisal well in the Libra area, the 3-BRSA-1255 (3-RJS-731), known as NW1. Located in the Northwest portion of the Libra block, in the pre-salt layer of the...

  • 24 November 2014

    Ensign secures contracts for 2 ADR 1500S pad drill rigs in Montney area

    Ensign Energy Services has signed contracts for two of its new ADR 1500S pad drill rigs for a major operator in the Montney area of northeast British Columbia...

  • 21 November 2014

    Statoil cancels Stena Carron rig contract offshore Angola

    Statoil has decided to cancel the Stena Carron rig contract after fulfilling the work commitments in the Statoil-operated blocks 38 and 39 in the Kwanza basin offshore Angola...

  • 19 November 2014

    Stepwise approach guides Statoil’s North American onshore path

    When Statoil entered the North American onshore industry in 2008, it was a non-operator in a joint venture (JV) with Chesapeake in one shale play. Since then, Norwegian-based…

  • Read more news