Drilling Rigs & AutomationNewsThe Offshore Frontier

2H Offshore installs fast-track retrofit conductor-supported platform offshore Bahrain.

2H Offshore completes the installation of a retrofit conductor-supported platform.
2H Offshore completes the installation of a retrofit conductor-supported platform.

2H Offshore has completed the installation of a retrofit conductor-supported platform (CSP). This enabled an appraisal well to be transitioned to production in 26 m water depth, offshore Bahrain, within six months of project award.

On behalf of BAPCo and Schlumberger, 2H Offshore designed a tripod CSP with boat landing that can support three surface trees with a total work area of just 90 sq m.

The platform was a particular challenge, as it was clamped retrospectively onto the drilled conductor under an already installed surface tree. Additional conductors were driven to provide support for the CSP and enabling two potential future wells. The CSP consisted of a subsea template, a top platform, top brace structure, single deck and boat landing.

Keeping the structures small reduces transportation costs and allows the use of the jackup rig for installation avoiding mobilization of a dedicated installation vessel. Together with the use of readily available standard material and local fabrication options, the modular and minimal CSP solution enables many opportunities to drive costs down.

The structure was installed entirely by Shelf Drilling’s Key Hawaii drilling rig, aided only by an observation ROV. In addition to the design and engineering, 2H Offshore managed fabrication and supervised offshore installation on-site in Bahrain. 2H subcontracted Arab Shipbuilding & Repair Yard (ASRY), Bureau Veritas, as well as sister companies Claxton Engineering and Seatronics, which all contributed to the completion of the project.

“Completing this project within the tight time frame despite the challenge of retrofitting it under an installed tree shows that with the right design and excellent network, a fast-track, lightweight, retrofit structure is an excellent choice for many shallow-water fields. Seamless collaboration with our clients, and the professionalism from ASRY, the local fabrication yard, ensured this project ran efficiently, to specification and on schedule,” Hassan Saleh, Principal Engineer at 2H Offshore, said.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button