NewsThe Offshore Frontier

Rigorous risk assessment, data-driven approach among keys to success in SIMOPS operations offshore Nigeria

Dick Verhaagen (left), VP Africa for Pacific Drilling, and Jimmy Jeansonne, Operations Manager Drilling & Completions Operations for Chevron, discussed the detailed planning and execution of close-proximity SIMOPS drilling and completions operations at the 2016 IADC Drilling Africa Conference in Cape Town, South Africa, on 16 February.
Dick Verhaagen (left), VP Africa for Pacific Drilling, and Jimmy Jeansonne, Operations Manager Drilling & Completions Operations for Chevron, discussed the detailed planning and execution of close-proximity SIMOPS drilling and completions operations at the 2016 IADC Drilling Africa Conference in Cape Town, South Africa, on 16 February.

To drill a gas-injector well that would support two high-rate producing wells on the Agbami field offshore Nigeria, Chevron and Pacific Drilling decided to conduct two close-proximity SIMOPS drilling and completion operations. More than 80 million barrels of incremental production stood to be gained, but risks had to be identified and mitigated. “One of the things that we agreed upon early was to make data-driven decisions,” Jimmy Jeansonne, Operations Manager Drilling & Completions Operations for Chevron, said in a presentation at the 2016 IADC Drilling Africa Conference in Cape Town, South Africa, on 16 February. He cited this data- and information-driven approach to decision making as one of the critical factors that led to the project’s success.

Due to the location of an existing subsea facility, the team faced limited subsurface options. They could either drill to a sub-optimum position in the reservoir, or reach the optimum position at an angle in excess of 70°, which would be difficult if not impossible to drill. “By moving the surface location closer to the FPSO within the anchor pattern, we were able to hit the optimum position in the reservoir and keep that approximately 45° which we felt very comfortable drilling,” Mr Jeansonne said.

Scheduling considerations in terms of equipment availability and limited drilling locations also were factors in the decision to conduct the close-proximity operations. In the first operation, the Pacific Bora drillship would drill in close proximity to Chevron’s FPSO. In the second operation, the Pacific Bora and Pacific Khamsin drillships would operate in close proximity to each other, as well as the FPSO.

Concerns for a myriad of potential unplanned events had to be addressed. “What happens if you had a power loss to the rig, and the rig drifted off? What happens if you had a drive-off situation? What happens if you had a supply boat emergency?” Mr Jeansonne asked. Further, there were infrastructure at risk of impact – the FPSO and rigs, subsea flow lines and umbilical, and mooring lines.

“To adequately assess the risks, we had 10 separate risk assessment sessions where we engaged a variety of stakeholders and subject matter experts,” he explained. These included everyone from Chevron’s asset development teams to facilities engineering teams to production operation teams, from supply management to HSE to the legal department. Corresponding groups at Pacific Drilling, as well as government partners, were included in these engagement sessions, as well.

To facilitate the data-driven decision making, the team calculated the probability for drive-off and drift-off collisions. The probabilities for drive-off and drift-off were based on IMCA dynamic positioning incident probabilities, while probabilities of the direction in which the events would occur were based on metocean data. Probabilities of non-recovery were also considered, based on Chevron case studies in drive-off situations and based on drills conducted with the drillships for drift-off situations. In the end, the team determined the overall drive-off collision probability to be 0.0753% and the overall drift-off probability to be 0.00404%.

Despite such low probabilities, the team recognized the project’s potential for high consequences. Multiple risk mitigation measures were identified through engagement sessions with stakeholder and subject matter experts, Mr Jeansonne said. For example, two tugs were hired to arrest any rig excursion. “We used ABS, as well as Chevron and Pacific marine experts, and worked together to properly size the tugs that we needed to control the rig in the event that we have a drift-off or drive-off,” he explained. “Secondly, we did extensive drills with those tug boats to make sure the crews knew exactly how to respond, could respond, in the quickest manner.”

For the second operation in which the two drillships would be working in close proximity to each other, DP officer coverage was increased on each rig. The team also ensured there was a clear command and control structure in place in the unlikely event of a DP issue. “In our case, we decided that the Pacific Khamsin Master would be in charge of both rigs in case of a situation related to DP or well control situations,” Dick Verhaagen, VP Africa for Pacific, said.

In the end, the Pacific Bora operated in close proximity to the FPSO for 70 days without events related to the close-proximity work. The Pacific Bora and the Pacific Khamsin operated in close proximity for 29 days without related events.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button